交通限制及延误
2018年9月7日至13日
SPOKANE COUNTY, September 7, 2018 – The road construction and maintenance is still in full swing, so please slow down when approaching a work zone and be alert for flaggers.
CONSTRUCTION
2018 Pavement Removal & Replacement
Removing existing pavement, & replacing the pavement and other work as needed (Regal Phase 1, Whitworth Phase 2, Liberty Phase 3). Spokane County Public Works: Construction: (509) 477-3600
Regal Rd: from 57th Av to 57th Av
Delay (Both Directions, All Lanes): Watch for Flaggers, be prepared to stop.
09/12/2018 - 10/31/2018
Whitworth Dr: from Hawthorne Rd to Wall St
Delay (Both Directions, All Lanes): Please watch for Flaggers, be prepared to stop.
09/12/2018 - 10/31/2018
Whitworth Dr: from US-395 to Hawthorne Rd
Delay (Both Directions, All Lanes): Be prepared to Stop, flaggers may be present
09/12/2018 - 10/31/2018
Liberty Dr: from Melkapsi St to Tum Tum Dr
Delay (Both Directions, All Lanes): Be prepared to Stop. Flaggers may be present.
09/12/2018 - 10/31/2018
Bigelow Gulch 5A
Improvement of the Bigelow Gulch Corridor connecting Forker Road to Progress Road via a new alignment north of the existing intersection (Forker & Progress). Spokane County Public Works: Construction: (509) 477-3600
Progress Rd: from Forker Rd to Spokane Valley City Limits
No Truck Traffic (Both Directions, All Lanes): Construction beginning on the next Phase of Bigelow Gulch. Work will be adjacent to Forker and Progress Road. Look for trucks entering roadway. 05/29/2018 - 12/31/2018
Forker Rd: from Jacobs Rd to Progress Rd
No Truck Traffic (Both Directions, All Lanes): Road is open. Work will start adjacent to
Forker, allow extra time, expect delays. Watch for Flaggers. Be prepared to stop.
05/29/2018 - 12/31/2018
Bigelow Gulch/Forker Intersection
Impacts to Bigelow Gulch from Palmer to Forker due to construction activities for the
reconstruction of the intersection. Spokane County Public Works: Construction: (509) 477-3600
Bigelow Gulch Rd: from Palmer Rd to Weile Av
Delay (Both Directions, All Lanes): TRUCKS ENTERING ROADWAY-Temporary Signal, be prepared to stop between the hours of 6am to 5pm Monday through Friday. Signal will flash yellow after hours. 02/12/2018 - 10/31/2018
Bigelow Gulch Rd: from Forker Rd to Forker Rd
Flaggers May Be Present (Both Directions, All Lanes): Drivers are now on the temporary alignment. Speed limit is 25mph from Evergreen to Progress, slow down, use caution and watch for workers adjacent to roadway. TRUCKS ENTERING ROADWAY-Please use caution. 02/12/2018 - 10/31/2018
Monroe Road Bridge
Remove and Replace Bridge Over Dragoon Creek
Spokane County Public Works: Construction: (509) 477-3600
Monroe Rd: from Bridge #2803 Over Dragoon Creek to Bridge #2803 Over Dragoon Creek - Road Closed: 05/14/2018 - 10/31/2018
Palouse Highway Sidewalk Project
Improvement of the Palouse Hwy and Sidewalks to include excavation, storm sewer, sidewalk, curb ramps and plantings. Spokane County Public Works: Construction: (509) 477-3600
Palouse Hy: from 57th Av to 61st Av
Lane Restrictions (Both Directions, All Lanes): Please watch for Flaggers, there will be delays. 08/14/2018 - 11/30/2018
Palouse Hy: from 55th Av to 57th Av
Lane Restrictions (Both Directions, All Lanes): Please watch for flaggers, there will be delays. 08/14/2018 - 11/30/2018
PRIVATE CONTRACTOR WORK BY PERMIT
513 E HASTINGS
CLOSE W/B RIGHT LANE OF HASTINGS AV BETWEEN DAKOTA & STANDARD ON 9/20 SO THAT TRUCKS CAN BACK INTO PARKING LOT - INLAND ASPHALT
Hastings Rd: from Dakota St to Standard Dr
Lane Closed (Westbound, Right Lane): CLOSE W/B RIGHT LANE OF HASTINGS AV
BETWEEN DAKOTA & STANDARD ON 9/20 SO THAT TRUCKS CAN BACK INTO
PARKING LOT. 09/13/2018 - 09/21/2018
BLOCK N/B WALL ST TO BUILD RISER ON POLE
BLOCK RIGHT (NORTH BOUND) LANE OF WALL STREET (BETWEEN IVANHOE &
BARNES RD) DURING WEEK OF 9/10/18 - 9/14/18 TO INSTALL NEW RISER ON POLE - AVISTA:
Wall St: from Ivanhoe St to Barnes Rd
Lane Closed (Northbound, Right Lane): BLOCK RIGHT (NORTH BOUND) LANE OF
WALL STREET (BETWEEN IVANHOE & BARNES RD) DURING WEEK OF 9/10/18 -
9/14/18 TO INSTALL NEW RISER ON POLE. 09/10/2018 - 09/15/2018
MAINTENANCE
(Road maintenance projects are subject to change due to weather conditions and other road maintenance priorities)
PROJECT ROSE UTILITY EXTENSION
CLOSE GEIGER BLVD TO INSTALL CITY SEWER & WATER TO PROJECT ROSE SITE ON GEIGER BLVD FROM HAYFORD RD TO THOMAS MALLEN RD 8/20/18 - 9/12/18 (3.5 weeks) - PEIRSOL CONSTRUCTION:
Geiger Bv: from Hayford Rd to Thomas Mallen Rd
Road Closed: CLOSE GEIGER BLVD TO INSTALL CITY SEWER & WATER TO
PROJECT ROSE SITE ON GEIGER BLVD FROM HAYFORD RD TO THOMAS MALLEN RD 8/20/18 - 9/12/18 (3.5 weeks). 08/20/2018 - 09/15/2018
Asphalt Patch
Repairing potholes County-wide, this dependent on weather conditions.
Spokane County Public Works-Maintenance: (509) 477-3600
Grading
Grading operations are dependent upon weather. A Burn Ban is still in effect and we cannot grade. If we get sufficient rain, roads will be graded. Spokane County Public Works-Maintenance: (509) 477-3600